case-studies
Filter
P
Pharma · Hyderabad
USFDA-aligned arc flash retrofit during a planned shutdown
A pharmaceutical formulation plant ahead of a USFDA inspection retrofitted
protection settings, hardware and PPE across 14 substations — entirely within
a 14-day shutdown window.
↓ 48%Avg incident energy
14 dShutdown
14Substations
A
Aluminium Smelter · Eastern India
From PPE Cat-4 to Cat-2 across 38 substations
An integrated smelter retrofit reduced incident energy across 38 substations,
downgraded PPE category for routine switching, and delivered an OSHA-defensible
compliance file in 11 weeks.
↓ 62%Avg incident energy
11 wkDuration
38Substations
S
Integrated Steel Plant · Eastern India
Group EHS standardisation across a 4-million-tonne facility
A Tier-1 steelmaker rolled out a group-EHS arc flash programme across blast
furnace, hot & cold strip mills and rolling. Outcome: a defensible
electrical-safety baseline in front of group HQ audit.
87Buses modelled
14 wkDuration
5Mills
Want a study like one of these for your plant?
Use the scoping tool for an indicative scope and timeline, or talk to a senior engineer about a peer reference closer to your industry and geography.